Construction

Construction Activities

  • The contractor completed the deck pour for span 22 on Sunday, December 2. (5 decks remain to be poured). The next deck pour is anticipated for Tuesday, December 11.
  • Work continues on Village Green Drive.
    • Traffic shift on Village Green. Eastbound and westbound traffic shifted to the north side of Village Green for utility work, drainage activities and reconstruction of the south side of Village Green.
    • One of two southbound left turn lanes are closed on US 1.
    • One southbound lane and one northbound lane closed on US 1 from Savanna Road to Village Green Drive Intersection.
    • Two southbound lanes on US 1 between Savanna Road and Village Green will be closed from 6 p.m. to 7 a.m. on December 16-21.
  • Trestle installation for the project is complete.
  • All pile driving for the project is complete (32 pile foundations).
  • All caps for the project are complete 1-32.
  • On Tuesday, the contractor set all beams for the project. (284 beams total)
  • Berm activities continue near Chaloupe area.
  • Pour sidewalk southside of the west approach next week.
  • Installing anchor bolts for Minnesota Rail on the bridge.
  • Decorative handrail started on the bridge.
  • Excavation for pond 2 continuing next week.

Special Events

Crosstown Parkway Extension Job Fair – June 29, 2017

Groundbreaking Event – May 9, 2017

Construction Open House – March 6, 2017

Design Open House – January 13, 2016

Road Closures / Traffic Updates

One northbound and southbound outside lane closed on US 1 from Veterans Memorial Parkway to Savanna Road on Wednesday, December 5 and Thursday, December 6 from 6 p.m. to 7 a.m.

Two southbound lanes closed on US 1 between Savanna Road and Village Green on Sunday, December 16 through Friday, December 21 starting at 6 p.m to 7 a.m. daily.

The eastbound traffic on Village Green was shifted towards the median area and southside of the roadway. A through lane in each direction and a left turn lane onto US-1 remain open. The roadway will remain in this configuration for construction activities including utility work, drainage and reconstruction of the north half of Village Green Drive.

One northbound lane on US-1, north of Village Green Drive intersection, will be closed through January, 2019. One of the two left southbound turn lanes from US-1 to Village Green Drive will be closed.

One US 1 southbound lane closure from Savanna Road to Veterans Memorial Parkway will be closed Monday through Friday from 9 a.m. to 4 p.m.

West Virginia Drive is closed from east of Sandia Drive to SE Coral Reef Street. Floresta remains open to traffic.

Please seek alternate routes to accommodate safety in this area. Alternate routes can include NE Prima Vista Boulevard, SE Thornhill Drive and SW Port St. Lucie Boulevard.

1436__Crosstown_Sandia-CoralReef_Map4

Channel Restrictions

Beginning on December 4, 2017 through April 30, 2018, the width of the channel of the North Fork of the St. Lucie River will be reduced to 33’ due to the construction of the temporary trestle (work platform).

The contractor will implement periodic height restrictions, allowing clearance for boats that are 6’ or lower only.

Height restrictions will be in place on the following dates. Dates may change due to weather and other unforeseen circumstances.

  • March 5 and 6
  • March 20 – March 30

Anticipated Timeline

Crosstown Revised Schedule_06_16_17