Thursday, Apr 26, 2018

Construction

Construction Activities

  • Placing base rock for the roadway west of Floresta Drive with a focus on the westbound lanes.
  • Began asphalt paving on Friday, April 13th.
  • Work continues on Village Green Drive.
    • One of two southbound left turn lanes will be closed on US 1.
    • Traffic from the north side of Village Green Drive from US 1 to Huffman Road was shifted to the south side of the roadway for utility, drainage and roadway activities.
    • One southbound lane closed on US 1 from Savanna Road to Village Green Drive Intersection.
    • Team is performing door to door outreach with the businesses in the area.
  • Contractor has installed 21 of 46 spans of trestle on the eastside.
  • The contractor will continue driving test piles on the east side of the NFSLR (test piles at bent 32, 31, 30, 29 and 28 are complete). The contractor completed driving production piles at end bent 32,31, 30 and 29. (21 of 32 bents driven to date.)
  • The contractor will start pile driving on the east side on Saturdays from 8 a.m. to 5 p.m., as necessary.
  • Beams installed over the North Fork of the St. Lucie River. (Completed spans 1 through 16.)
  • Installing form work for deck spans 7-10.
  • Segmental block wall has been completed on the west side of the project.

Special Events

Crosstown Parkway Extension Job Fair – June 29, 2017

Groundbreaking Event – May 9, 2017

Construction Open House – March 6, 2017

Design Open House – January 13, 2016

Road Closures / Traffic Updates

The northbound traffic on Village Green will be shifted towards the median area and southbound roadway. A through lane in each direction and a left turn lane onto US-1 will remain open. The roadway will remain in this configuration for three to five months for construction activities including utility work, drainage and reconstruction of the north half of Village Green Drive.

One of the two left southbound turn lanes from US 1 to Village Green Drive will be closed.

West Virginia Drive is closed from east of Sandia Drive to SE Coral Reef Street. Floresta remains open to traffic.

Please seek alternate routes to accommodate safety in this area. Alternate routes can include NE Prima Vista Boulevard, SE Thornhill Drive and SW Port St. Lucie Boulevard.

1436__Crosstown_Sandia-CoralReef_Map4

Channel Restrictions

Beginning on December 4, 2017 through April 30, 2018, the width of the channel of the North Fork of the St. Lucie River will be reduced to 33’ due to the construction of the temporary trestle (work platform).

The contractor will implement periodic height restrictions, allowing clearance for boats that are 6’ or lower only.

Height restrictions will be in place on the following dates. Dates may change due to weather and other unforeseen circumstances.

  • March 5 and 6
  • March 20 – March 30

Anticipated Timeline

Crosstown Revised Schedule_06_16_17