Friday, Oct 19, 2018

Construction

Construction Activities

  • The contractor is providing a tour of the project for two local Boy Scout Troops on Saturday.
  • The next deck pour for span 26 is anticipated on Tuesday, October 9, weather permitting. (21 out of 31 decks poured to date)
  • Work continues on Village Green Drive.
    • Traffic shift on Village Green. Eastbound and westbound traffic shifted to the north side of Village Green for utility work, drainage activities and reconstruction of the south side of Village Green.
    • One of two southbound left turn lanes are closed on US 1.
    • One southbound lane and one northbound lane closed on US 1 from Savanna Road to Village Green Drive Intersection.
  • Trestle installation for the project is complete.
  • The contractor completed driving test piles on the east side of the NFSLR. The contractor completed driving production piles at bent 20 and 19. (31 of 32 bents driven to date.)  Pile driving is anticipated to be complete by the end of next week.
  • Beams installed on spans 1 through 16 and 24 through 31.
  • Installing form work for deck spans 25 and 26.
  • Installing chain link fences along the right-of-way behind residential properties.
  • The contractor is painting the deck edge and beams on the project.
  • The contractor is working on the median barrier wall on the west side.

Special Events

Crosstown Parkway Extension Job Fair – June 29, 2017

Groundbreaking Event – May 9, 2017

Construction Open House – March 6, 2017

Design Open House – January 13, 2016

Road Closures / Traffic Updates

The northbound traffic on Village Green was shifted towards the median area and southbound roadway. A through lane in each direction and a left turn lane onto US-1 remain open. The roadway will remain in this configuration for construction activities including utility work, drainage and reconstruction of the north half of Village Green Drive.

One northbound lane on US-1, north of Village Green Drive intersection, will be closed through December 13, 2018. One of the two left southbound turn lanes from US-1 to Village Green Drive will be closed.

One US 1 southbound lane closure from Savanna Road to Veterans Memorial Parkway will be closed Monday through Friday from 9 a.m. to 4 p.m. until October 10, 2018.

Huffman Road will be closed between US 1 and Village Green Drive from September 10 – September 21 for drainage activities.  Businesses will remain open.

West Virginia Drive is closed from east of Sandia Drive to SE Coral Reef Street. Floresta remains open to traffic.

Please seek alternate routes to accommodate safety in this area. Alternate routes can include NE Prima Vista Boulevard, SE Thornhill Drive and SW Port St. Lucie Boulevard.

1436__Crosstown_Sandia-CoralReef_Map4

Channel Restrictions

Beginning on December 4, 2017 through April 30, 2018, the width of the channel of the North Fork of the St. Lucie River will be reduced to 33’ due to the construction of the temporary trestle (work platform).

The contractor will implement periodic height restrictions, allowing clearance for boats that are 6’ or lower only.

Height restrictions will be in place on the following dates. Dates may change due to weather and other unforeseen circumstances.

  • March 5 and 6
  • March 20 – March 30

Anticipated Timeline

Crosstown Revised Schedule_06_16_17