Construction Activities

  • The bridge and roadway are open to traffic from Manth to U.S. Highway 1. Lane closures are anticipated throughout the project for construction activities and deficiency list items.
  • The contractor started responding to damage claims and will continue to work to close out opened damage claim requests.
  • Pending Project Items:
    • Sod installation under the bridge at Coral Reef and in various areas throughout the project.
    • Final thermo left on Coral Reef, Manth and turn lanes at Floresta.
    • Construction of the plaza under the bridge including lighting, irrigation, brick pavers, sidewalks, landscaping, shell concrete and other decorative features.
    • Sign installation and corrections throughout the project.
    • Landscaping and mulching ongoing
    • Corrections and deficiency items
    • Fence installation continues
    • Name bricks installed at Plaza
    • Trellis installation pending.
    • Benches and trash cans to be installed.

A final inspection will take place prior to project acceptance.  The contractor continues to complete activities and corrections throughout the corridor.

Road Closures / Traffic Updates

Periodic lane closures on Crosstown from Manth Lane to east of US Highway 1 for the Contractor to finalize construction activities and work on punch list items.

Coral Reef remains closed under the bridge for construction activities.

Periodic one lane closures needed on US Highway 1 northbound and southbound.

Channel Restrictions

Evans Creek at the newly constructed Crosstown Bridge will be temporarily blocked until the end of February 2019.

Anticipated Timeline

Crosstown Revised Schedule_06_16_17